1. Site purchase transaction closed January 16, 2018
2. 1st Planning Commission Meeting Held April 11, 2018. - Status: Hearing to be Continued.
3. 2nd Planning Commission Meeting Held July 11, 2018. - Status: Approved.
4. 1st Architectural Review Committee Meeting Date: August 6th, 2018.
5. 2nd Architectural Review Committee Meeting Date: September 17th, 2018.
6. Project Approved! September 17th, 2018
7. Project Construction Working Drawings Commenced
8. Site remains master leased and producing income for the Partnership.